PLANNING DISASTERS FOR THE TWENTY-FIRST CENTURY
One
noteworthy absence from the many distinguished guests attending the recent
opening of the extension to the National Library of Wales by the Queen in May
1996 was any representative of the British Library, although invitations had
been issued. Some cynical observers wondered whether this was in any way related
to the fact that the new building in Aberystwyth was opened on time and to
budget in the same month as the publication of the report by the Comptroller and
Auditor General cataloguing the succession of delays and disasters in the
completion of the new British Library building at St Pancras (National Audit
Office, 1996).
The
two projects are not really comparable in scale however, for the new British
Library will perhaps be the one truly great new British public building to be
open and operational in time for the millennium. Yet the eventual com pletion of
this project around the autumn of 1998 will hardly be a cause for celebration
nor will it be seen as a mark of the confidence in which the British government
and society generally places in its national library service. Whatever one
thinks of Colin St John Wilson's new building, the sorry tale of inefficiency,
ineptitude, and mis-management during the planning and completion of the
project, have been the most notable feature of the press coverage of the library
for the last six years, and will also probably continue to be so for many years
to come. Unfortunately these problems will tend to overshadow any clear
assessment of the merits or otherwise of the new building, and of its
suitability as a national library for the twenty-first century. They will also
tend to impact upon the reputations of all those directly involved in the
project, irrespective of where the fault lies.
The
technical failures and problems associated with the construction of the building
have already been highlighted in an examination by the Committee of Public
Accounts (1991) and an earlier report from the National Audit Office (1990),
together with the latest and most damming report referred to above. These
explain exactly how the original project has been severely curtailed, and yet
has grown enormously in cost, and why the completion is now a decade behind
schedule. Yet some of the wider problems, and the indecisiveness and failings in
vision by various British governments were dealt with in Sir Anthony Kenny's
1994 pamphlet, published by the British Library. Taken together these documents
will make an excellent case study on how not to plan and execute a new library
service, and will represent a most striking contrast to the determination of the
French government to complete the Bibliotheque Nationale de France. It is
perhaps worth providing a brief summary of the main events in the prolonged and
sad tale of the planning and construction of what ought to have been an object
of pride for the whole library and information community of the UK.
In
1857, just over a century after the foundation of the national library
collection in the British Museum, Panizzi s great domed reading room was opened
to the public, built within the original quadrangle of the museum. The Round
Reading Room has been the symbol of the library ever since and according to
Kenny is much loved by those who use it. Yet in spite of the impressive
architectural qualities it is clearly no longer suited to its original purpose,
nor has it been for many decades. As a reading area it is both disconcertingly
noisy and distracting and the conflicting movements of staff, readers, and book
trolleys are both inefficient and can cause congestion. Above all however, the
once ample provision of cast-iron book stacks in the four corners of the
quadrangle were beginning to be exhausted by the end of the nineteenth century,
and available space was soon filled. As a result the last century has seen the
progressive movement of more and more books away from the readers with
consequent delays in the provision of material, or the need to visit more than
one site. The bulky collections of modern newspapers were transferred initially
to a repository and subsequently to a Newspaper Library at Colindale in 1932,
but it was only after the second World War that it began to be apparent that a
new library building, separate from the collections of the museum would soon be
required to house the rapidly growing collections.
It
will have taken more than 50 years from the inception of the new building to its
opening to the first group of readers. In 1947 seven acres adjoining Great
Russell Street, opposite to the Museum, were identified by the Trustees as a
possible site for a new building. After many delays, the architects Sir Leslie
Martin and Colin St John Wilson were commissioned to design a building in 1962,
which they submitted two years later. Unfortunately, the choice of this site
proved to be politically unacceptable as it would have involved the demolition
of several streets of Georgian houses and a Hawksmoor Church, and the plans were
rejected in 1967. As a result, from the 1960s lesser used books from the
Museum's collections began to be transferred to repositories at Bayswater and
Woolwich, as further storage space at Bloomsbury was in such chronic short
supply. Also, the demand for readers' places, particularly during the summer
months, frequently exceeded supply, and had artificially to be limited.
In
1971, a government 'White Paper' proposed the formation of the British Library
by the amalgamation of a number of collections of national importance, including
those of the British Museum and the National Reference Library for Science and
Invention (formerly the Patent Office Library). Both of these collections were
then identified as bursting at the seams and in urgent need of re-housing. The
new national library service was duly establishe.l in 1973 and further plans
were laid for an alternative new building for the two reference collections in
Bloomsbury. However, due to a combination of local opposition to further
building in Bloomsbury, and the availability of a vacant site adjacent to St
Pancras Station, the government decided that the new library building would be
some distance away from the museum.
Although
the St Pancras site was not ideal in terms of its location, it did at least
provide ample space for a magnificent library, occupying 200 000 square metres,
housing 3 500 readers and 25 million books. Plans for such an ambitious scheme
were agreed in principle by Ministers in 1977, to be completed in three phases.
The first and most important of the phases would be of 108 000 square metres and
be sufficient for the key needs of the library until the end of the 1980s.
Phases 2 and 3 planned for additional office accommodation and reader places
likely to be needed in the twenty-first century, and would be commenced at a
date to be decided. The first phase was to be further subdivided into Phases 1A,
1B, and 1C, in order to defer expenditure commitment to the whole project, and
indeed Phase 1A was further divided into sub-sub Phases 1AA and 1AB. The
breaking down of this ambitious project into such small parts and the lack of
any overall financial commitment to the whole sowed the seeds of the highly
complex and inefficient management of the project that would ultimately prove to
be so wasteful in time and money.
Permission
to go ahead with Phase 1AA of the library was given in March 1978, with
construction on site due to begin in 1979. However, the change of government in
the summer of that year meant a further one-year delay whilst the project was
re-assessed. Permission was again granted in 1980, although to proceed at a
somewhat slower rate than had originally been envisaged, due to need to reduce
government expenditure. Thus construction work did not begin until the Spring of
1982, and full financial approval for all parts of Phase 1A was not secured
until April 1987, with a then estimated completion date of 1993. Additional
complications were due to fundamental changes in government departmental
responsibilities during the late 1980s and early 1990s and the privatization of
the work of the Property Services Agency (PSA). Thus the transfer of financial
responsibility for the building passed to the Office of Arts and Libraries (OAL)
in April 1988, which in turn was subsumed in the Department of National Heritage
(DNH) in 1992, and the appointment of the British Library's own project managers
in October 1989 to oversee the acceptance of the building on behalf of the OAL
and plan their own future occupation.
It
was not until 1988 that there was any overall budget for the construction of
Phase 1 A of the building, including the reading rooms for Science Technology
and Industry, and for Rare Books, Music and Manuscripts, the closed access book
storage and an auditorium. Until then construction had to be planned and proceed
year by year on the basis of available funding. However in that year a cash
limited budget of £300 million was agreed. Likewise in July 1990 the government
allocated a further £150 million for the completion of Phases 1B and 1C
incorporating the General Humanities Reading Room, accommodation for the
Oriental and India Office Collections, the King's Library and a restaurant, all
with a planned completion date of October 1996. However at the same time, in
return for committing itself to the funding of these stages, the Treasury was
seeking ways of scaling down the original ambitious project. A study was
instituted into how the building might be completed to meet the key requirements
of the library, which in essence meant that Phases 2 and 3 would be abandoned,
and the land upon which it would have been built was to be sold off once the
building was complete. It is hard to imagine any more crass and short-sighted
decision, that would prevent any future government with more long-term vision
from fulfilling a plan that the present one felt unwilling or unable to
complete.
Thus
the new library, once it is eventually occupied, will be barely adequate for the
needs of its existing users, who have had to put up with all kinds of delays and
other difficulties for decades. There will be no significant opportunities to
develop new services. Many of the reading rooms will not be able to cope with
the expected increase in usage once the new building becomes fully operational,
and the advantages of bringing together at one site the enormous information
resources avaiable, become apparent to scholars. Likewise the enormous book
stores will be almost full immediately and the need for further off-site storage
will soon become apparent. Above all, there will be no leeway to maintain an
acceptable level of the present service until such time as the impact of
electronic storage and delivery systems can be fully evaluated and necessary
changes to working practices implemented.
All
of these problems with the new library might have been bearable had the project
been well managed and not subject to further delay since it took its final shape
in 1990. However the recent National Audit Office report (1996) identifies a
catalogue of disasters in the management and technical implementation of the
project causing further delay and expense whilst remedial work was implemented.
Problems with the quality and reliability of the mobile book shelving, damage to
electrical cabling, poorly designed ducting, and the need for better emergency
lighting are among the 230 000 defects in the building that have been identified
to date. The National Audit Office report uses remarkably restrained language to
try to identify the causes of these problems and above all the key lessons to be
learned for other such projects in the future. The overall impression gained was
that the mistakes were due to a lack of foresight and commitment to the ideals
of project as a whole by government, rather than any incompetence by individual
employees. Yet as was pointed out in an editorial in the Daily Telegraph (1995)
it has not been by government standards a particularly expensive building. New
headquarters for the security services and new office accommodation for
Parliament are likely to prove equally expensive, but have not been subjected to
the short-sighted and penny-pinching funding of government, nor the public
scrutiny afforded to this project.
At
the same time as the debacle over the construction of the new building there has
also been the inevitable illinformed sniping at its outward appearance and the
stark contrast between its restrained features and the Victorian exuberance of
the neighbouring St Pancras station, or indeed the architectural splendour of
the British Museum. These have come from both tradionalists who will mourn the
loss of the Round Reading Room, and modernists who foresee the imminent
redundancy of printed books and indeed the need for traditional collections and
reading rooms. However, the inability to appreciate or cherish examples of great
contemporary architecture has been one of the abiding problems of British
society for generations, and no doubt our successors will be able to make a far
better assessment of the design than we are currently able to do.
No
doubt all of the remaining problems with the building will soon be resolved and
readers will be able to take advantage of what, for many years to come, will
inevitably be a fine library. Yet the prolonged gestation, and the missed
opportunities of this project must be an object of regret, and indeed shame, to
all those who believe that libraries are a fundamentaly important part of our
heritage.
David
Stoker
REFERENCES
Committee
of Public Accounts (1991) 18th Report. London: HMSO (HC 132 1990-91)
Daily
Telegraph (1996)
'Catalogue of disasters' [editorial]. 15 May
Kenny,
Anthony (1994) The British Library and the St Pancras Building. London:
The British Library
National
Audit Office (1990) New building for the British Library. London: HMSO
(HC 650 1989-90)
National
Audit Office (1996) Progress in completing the new British Library. London:
HMSO (HC 362 1995-1996)
JOURNAL
OF LIBRARIANSHIP AND INFORMATION SCIENCE, 28 (3) SEPTEMBER 1996 131